MANAGER’S REPORT
11 August. 2009
The
recent prolonged heat required the District to run at maximum flows for a few
weeks, but the recent weather has provided some needed relief allowing flows to
back off slightly. Overall demand on the
The
Juniper Ridge Pipeline and Hydroelectric Project is proceeding through its
financing and contracting stages. Oregon
Department of Energy is preparing the final closing documents for the project’s
construction financing,
The Habitat Conservation Plan is continuing under its existing grant from the US Fish & Wildlife Service. The DBBC is requesting a reallocation and extension of spending deadlines in order to continue biological work past September 2009 and keep the HCP effort moving despite not receiving a grant for the HCP for the next federal fiscal year. A grant application for roughly $400,000 of HCP funding was filed last week. It is anticipated to know the results of this grant request in the spring of 2010.
A
federal court recently issued a remand to the US Fish & Wildlife Service on
the 2007 Bull Trout Critical Habitat Plan (CHP). COID and the Deschutes Basin Board of Control
is evaluating the remand and preparing for filing comments later this fall. The DBBC was very involved in the last CHP
process and is another species involving the Endangered Species Act and the
The opportunities pursued this past month include, but are not limited to:
·
The City of
·
· The Deschutes Water Alliance (DWA) is moving forward with Water Bank transactions and planning for 2009. There is movement to expand active participation of the counties and elected officials and to formalize the partners’ relationships with memorandums of understanding or other forms of agreement for existing and future coordination on regional water issues.
· Kevin Crew with Black Rock Consulting is facilitating the process for a 20 Year District Capital Improvement Plan (CIP). Preliminary evaluations and data gathering are already underway with staff coordination and information on the entire irrigation system. A draft concept is anticipated for Board discussion this winter.
·
COID has re-engaged Pacific Power in
conversations over termination of their lease and hydro facility at
· COID is coordinating with BLM staff on operational issues involving BLM owned and COID owned lands and where COID has federal 1891 Rights of Way.
· COID is coordinating discussions between the US Forest Service and the Bureau of Reclamation on clarifying operational boundaries at the Crane Prairie Dam.
The challenges presenting themselves:
· Issues continue to arise with patrons and the delivery of water to parcels past the District’s Point of Delivery. The District is evaluating its existing statutory authorities and reviewing policies to assist in resolving these issues.
STATUS REPORT
Juniper
Ridge Piping & Hydroelectric Project
· Weekly project status meetings with contractor team
· The interconnection and power purchase agreements are proceeding with PacifiCorp. The PPA is anticipated to be ready for signature this week.
· OWEB approved $1 MM project grant
· Received $250,000 as restoration grant from Pelton – Round Butte Restoration Fund provided by Portland General Electric and the Confederated Tribes of Warm Springs.
· ODOE Small Energy Loan Program approved $17 million in project financing. ODOE loans carry only a revenue obligation of the project and can not encumber patron assessments.
· Business Energy Tax Credit application has received its necessary pre-certification. COID is now eligible to market the tax credits to individuals and entities that have Oregon State Tax obligations.
· DEQ State Revolving Fund announced Juniper Ridge as a special green project and to receive $2 MM in grant and $2MM in 20 year 0% interest loan.
·
FERC conduit exemption application submitted
with full NEPA and state and federal agency support. Application to the State of
· Grant request of $5 million submitted to the US Bureau of Reclamation under the Water Conservation Initiative program funded by the federal stimulus package.
·
City of
· Cooperative
evaluation of potential 50-100 acre re-regulating structure on
Status
– In Process with no change in last month
Real
Estate
· One 20 acre
parcel near
Status – In Process with no change in last month
· COID and
the
Status – In Process. Joint meetings being conducted with
City of
·
A Conditional
Use permit was received for COID owned lands along
Status – In Process with no change in last month
Development
· Direct communication with City of Bend and Redmond public works and planning staff on resolving issues of canal safety and impacts of development that will require piping.
Status – In Process.
Preliminary discussions held, issues ongoing, no resolution expected for
some time.
ON THE RADAR SCREEN
· Bull Trout Draft Recovery Plan
· Pursuit of funding designations with Bonneville Power Administration for conservation projects above Pelton Round Butte complex